Project Outputs lists every calculation you have accepted for the active project, what each one costs, and whether it is paid. When everything is paid, this is where you download the project documents.

The Project Outputs page#

Click Project Outputs in the sidebar. The header shows the project and job number.

Accepted calculator outputs included#

This table has one line per accepted calculation. Its columns are Accepted output, Type, Price, Status and Actions.

  • Status shows Paid, Unpaid or Price not configured.

  • Extra notes can appear under a calculation's name:

    • an amber message if Project Settings changed after it was assessed;

    • "Revision N - current version";

    • "Revision N - replaces the accepted version once paid";

    • "Draft revision N in progress".

  • The Actions menu (⋮) changes with the line's status:

    • Unpaid: Edit Calculation and Delete Calculation.

    • Paid: View Calculation and Revise Calculation, plus Revision History once it has been revised.

    • A revision's own line: Open Revision, plus Remove Revision while it awaits payment.

If nothing has been accepted, the table reads "No accepted outputs yet. Accept a calculation to see it here."

Download document packs#

The right-hand column has the payment panel while anything is unpaid, then the downloads. See Pay and download.

What the package contains#

DownloadWhat it holds
Project Summary.pdfA project information page (the site, its geotechnical basis, and the ground bearing capacity each calculation was assessed with). Then a summary of each accepted calculation with its mark (such as L1, FB1, P1) and revision. Then a drawing schedule.
Structural Calculations.pdfThe calculation pages from every accepted calculation.
Structural Drawings.pdfThe drawing pages from every accepted calculation. This includes the Support Schedule and the Pad Details sheet where the design needs them.
Download AllAll Project Documents.zip, with the three PDFs above.

Each PDF starts with a project title page. Page 1 carries a VERIFY DOCUMENT block with a QR code and the document reference (for example AS000123.0). Every page has a footer with the reference, revision, issue date and page number. See Verify a document.

Issued documents and revisions#

  • The first successful download after payment, and after release where review applies, is the issue. ArchiSuite stores the exact files it delivered. Before that first download you are asked to confirm (Issue and download documents): press Continue and Download to issue, or Cancel to leave the project as it is.

  • Every later download of that revision returns the same files. Nothing is re-created, so a later calculator or template change cannot alter them.

  • If the accepted calculations change, for example after a paid revision, the next download issues a new revision. The reference goes from .0 to .1, then .2. The previous revision is marked superseded and kept. It is never overwritten.

Document History#

Click Document History in the sidebar, or the Document History → link on Project Outputs. Each formal issue shows:

  • its reference and revision;

  • its status: current, superseded, withdrawn or draft;

  • the issue date, and the module.

From each issue you can:

  • View passport, which opens the public verification page;

  • Copy verification link;

  • Download original, which gives the exact issued file for each document type. It is greyed out while an ArchiSuite review is in progress.

  • Create revision (current issue only). Enter a Revision description (required) and press Create revision. The current issue is marked superseded and kept. Only Administrators and Editors can do this.

If there are no issues yet, the page reads "No formal issues yet. Generating a download pack creates the first issue automatically."