Troubleshooting

Why an Input Is Refused

What the red messages under an input and the error toasts after Analyse mean, grouped by cause, with the fix for each.

On this page

ArchiSuite checks your inputs twice. The form checks them as you type. The server checks them again when you press the analyse or update button. Either way, nothing is saved or calculated until every input is accepted.

Where the message appears#

  • Under the input, in red. This is the form's own check. The button does nothing until you fix it.

  • As a toast after pressing Analyse or Update. The server refused the request. The toast shows the server's reason.

Messages on the form#

Missing values#

  • "Required": the input is empty. Fill it in.

  • "Calculation name is required": give the calculation a name in the first section.

  • "Name is required": each point load or pad needs a name.

Out of range#

  • "Allowed range: 0 – 8 m" (the numbers vary by input). Enter a value inside the range shown.

  • "Maximum is 10m", "Must be at least 0.1m", "Must be >= 0", "Must be > 0 mm", "Must be ≤ 3000 mm", "Minimum is 26°", "Maximum value is 300 kPa" and similar messages give the limit directly.

Check the units first. Spans and loaded dimensions are in metres. Retained heights are in millimetres. A value typed in the wrong unit is the most common cause of an out-of-range message.

Each calculator's guide lists every input's accepted range.

Load signs (foundation calculators)#

  • "Must be strictly negative (< 0)": down reactions such as 1.35G (kN) and 1.2G + 1.5Q (kN) are entered as negative numbers.

  • "Must be strictly positive (> 0)" (Square Pad Foundation): the uplift case, 0.9G + Wu, is entered as a positive number.

Either one or the other#

Some loads can be entered in two ways. For a roof, give the Roof loaded dimension (m), or the Eave / overhang (m) and the Roof span (m). For a floor, give the Floor loaded dimension (m), or the floor joist span. The exact labels vary slightly between calculators.

When you fill in one way, the form clears the other way's inputs. On the foundation forms they show "Not used - loaded dimension entered" or "Not used - span/eaves entered". If both are sent, the server answers "Enter either the roof loaded dimension or the roof span and eaves width, not both." (or the floor version). Clear one of them.

When you use the span route on the lintel calculators, the loaded dimension used is the eave / overhang plus half the roof span (roof), or half the floor joist span (floor). So enter the full span, not half of it.

Supporting stud height#

On the lintel and beam calculators, Supporting stud height (m) must be within "Allowed range: 0.3 – 4.0 m". Set it with the input or the slider on the diagram.

Messages from the server (toasts)#

  • "Failed to create … calculation" or "Failed to update …" with no other detail: the server refused one of the inputs. Check each input against its range, then press the button again.

  • "This project already has a calculation named '…'. Give this one a different name, so its drawings and calculations can be told apart." Rename the calculation.

  • "Project Settings … is required before running this calculation." or "Project Settings … must be between … and …": a Project Setting is missing or out of range. See Project Settings missing or out of range.

  • "Required input missing: …" or "The inputs are incomplete or not valid numbers.": an input was left blank or is not a number. Fill in the input named.

  • "Failed to select … beam" after pressing Select: that member could not be selected. Press Select on a different passing member.

  • "These inputs differ from the project geotechnical properties. Check they are suitable before continuing." (retaining walls): press Review inputs to change them, or Continue to run with your values.

  • "This page was opened for …, but your active project is now … Nothing was saved." You changed the active project in another tab. Make the original project active again, or reload the page.

  • "Admin or editor role is required for calculator changes." Viewers cannot analyse or save. Ask a team Administrator to change your role.

  • "This calculation has been accepted and paid for, so it cannot be changed." Use Revise Calculation. See Revise an accepted calculation.

Use the (i) help#

Many input labels have an (i) next to them. Click it to open that input's ArchiGuide help in a side panel. The help explains What it means, How to determine it and Common mistakes. Check it whenever you are unsure what a value should be.

If the values are right but your situation is outside what any calculator accepts, see When no calculator fits.

Was this helpful?