You need a structural engineer when the structure of your building work cannot be taken straight from NZS 3604 or another Acceptable Solution, so it has to be "specifically designed". For houses this usually means work outside NZS 3604's scope or tables: steel beams, portal frames, beams carrying point loads, buildings on poor ground, very windy or high-snow sites, and many retaining walls. For ordinary timber-framed work inside NZS 3604, a Licensed Building Practitioner (LBP) designer can normally do the design without an engineer.

What does NZS 3604 cover, and where does it stop?#

Most New Zealand houses are designed to NZS 3604:2011 Timber-framed buildings (opens in a new tab), which Acceptable Solution B1/AS1 cites, with modifications, as a way to comply with Building Code clause B1 Structure. MBIE notes that by limiting building size and scope, NZS 3604 lets a designer select a member or detail without engaging a structural engineer. Outside those limits, the design must be done some other way, usually by specific engineering design (SED).

Limits you can check in the published guidance include:

  • Ground: the building must be on "good ground". B1/AS1 (second edition) says foundations where good ground has not been established and the ground could liquefy or spread laterally are outside its scope.

  • Height and storeys: up to 10 m high and a maximum of three storeys, with the third storey a part storey in the roof space.

  • Wind: NZS 3604 wind zones run from Low to Extra High (55 m/s). Sites that the standard's wind zone table marks "SED" are outside its scope.

  • Snow: the main wall and roof framing tables include a 1 kPa snow load, with additional tables for 1.5 kPa and 2 kPa.

  • Floor loads: uniformly distributed floor loads are capped at 3 kPa.

  • Anything not detailed: MBIE states that design details not included in NZS 3604, or variations to its details (such as different fixings), need specific design.

Roof trusses are a special case: their design requires SED, but trusses from an accredited manufacturer that meet the standard's requirements are treated as part of the Acceptable Solution.

Which home projects usually need an engineer?#

SituationWhy it goes beyond the standard tables
Removing or altering an internal load-bearing or bracing wallNot exempt from consent under Schedule 1 clause 11; the replacement beam, its supports and lost bracing must be designed
A beam or lintel carrying a girder truss or other point loadBRANZ notes the NZS 3604 lintel tables do not provide for concentrated loads
A steel beam or steel columnNZS 3604 is a timber standard; details not in it need specific design
A portal frame to brace a wide openingResidential portals are specifically designed; Engineering New Zealand publishes guidance for engineers
A retaining wall outside the Schedule 1 exemptionWalls retaining more than 1.5 m of ground, or carrying a surcharge such as a driveway, need consent and a design
Poor, soft, expansive or liquefaction-prone groundOutside the "good ground" basis of NZS 3604 and B1/AS1
Larger or taller buildings, very windy or high-snow sites, heavy floor loadsOutside NZS 3604's scope limits

Two points about consent are easy to miss. First, a consent exemption does not remove the need to comply: section 17 of the Building Act says all building work must comply with the Building Code whether or not it needs consent. Second, some exemptions only apply when an engineer is involved. For example, Schedule 1 clause 41 exempts a retaining wall in a rural zone that retains up to 3 m of ground (and is at least its own height from boundaries and buildings) only where a chartered professional engineer carried out or reviewed the design.

What is the difference between an LBP designer and a CPEng engineer?#

LBP designers. Design of a home's primary structure is restricted building work when it needs a building consent, so it must be carried out or supervised by an LBP licensed in design. The Design licence has three areas of practice tied to building categories: Design 1 covers Category 1 buildings, Design 2 covers Categories 1 and 2, and Design 3 covers Categories 1 to 3. LBPs must work within their competence, and the LBP Board's guidance expects designers to seek help from a suitably qualified person when a job goes beyond it.

Chartered Professional Engineers (CPEng). Engineers are registered as CPEng under the Chartered Professional Engineers of New Zealand Act 2002, with Engineering New Zealand acting as the Registration Authority. Registered architects and chartered professional engineers are automatically treated as LBPs for restricted building work.

In practice, an LBP designer often prepares the house design to NZS 3604 and brings in a structural engineer for the parts that fall outside it, such as a steel beam, a portal frame or the foundations on difficult ground.

Where do producer statements fit in?#

Engineers often support their design with a producer statement. MBIE describes four types: PS1 (design), PS2 (design review), PS3 (construction) and PS4 (construction review). Producer statements have no particular status under the Building Act; a council decides whether to rely on one and will usually check the author's credentials. A council can also make it a condition of consent that a CPEng monitors construction and provides a PS4. See What is a PS1 producer statement? for more.

How do you engage a structural engineer?#

  1. Describe the job clearly. Gather any existing plans, photos of the area, and what you want to change (for example, "remove the wall between kitchen and lounge").

  2. Find a registered engineer. Search the CPEng register (opens in a new tab) by practice field and location, and check whether any notice is recorded against the engineer.

  3. Agree the scope in writing. Typical items are a site visit, calculations, drawings or sketches for the consent, a PS1, and any construction monitoring the council may require.

  4. Connect the engineer with your designer and builder. For residential work, MBIE notes that LBPs must provide a certificate of work for engineering design of the primary structure, and any restricted building work on site must still be carried out or supervised by an LBP, even where an engineer monitors construction.

  5. Consider ground advice early. If the site may not be good ground, a geotechnical assessment may be needed before foundations can be designed.

Key points#

  • Most timber-framed house work inside NZS 3604's limits can be designed by an LBP designer without an engineer.

  • An engineer is needed when work falls outside NZS 3604 or B1/AS1: steel members, portal frames, point loads, poor ground, very windy or high-snow sites, and many retaining walls.

  • Removing a load-bearing or bracing wall needs a building consent and a proper design.

  • Consent exemptions never remove the duty to comply with the Building Code (section 17).

  • Check engineers on the CPEng register and agree in writing what they will provide, including any producer statements.

Sources

  1. Building Act 2004 (version as at 8 October 2026) - section 17 and Schedule 1 (clauses 11, 20 and 41) (opens in a new tab) - New Zealand Legislation (accessed 20 November 2026)
  2. Using NZS 3604 Timber-framed buildings (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  3. Important modifications (Building structure documents - changes in 2011) (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  4. Acceptable Solution B1/AS1 Structural provisions for buildings, second edition (effective 28 July 2025) (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  5. NZS 3604:2011 Timber-framed buildings - SPONSORED (scope summary) (opens in a new tab) - MBIE Building CodeHub (accessed 20 November 2026)
  6. Wind zones and NZS 3604 (opens in a new tab) - BRANZ (accessed 20 November 2026)
  7. Loaded dimension (opens in a new tab) - BRANZ (accessed 20 November 2026)
  8. 3.3 Internal walls and doorways in existing building (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  9. Restricted building work (RBW) (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  10. Use licensed professionals for restricted building work (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  11. Licensing classes (opens in a new tab) - Licensed Building Practitioners (MBIE) (accessed 20 November 2026)
  12. Codewords 96: Competence in Design (opens in a new tab) - Licensed Building Practitioners (MBIE) (accessed 20 November 2026)
  13. Registration Authority - Chartered Professional Engineers (opens in a new tab) - Engineering New Zealand (accessed 20 November 2026)
  14. Find a registered engineer (opens in a new tab) - Engineering New Zealand (Registration Authority) (accessed 20 November 2026)
  15. Producer statements (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)