When do you need building consent in New Zealand?

Building work in New Zealand needs a building consent unless the Building Act exempts it, mainly in Schedule 1. Exempt work must still meet the Code.

Author
ArchiSuite
Checked against sources:
Published:
On this page

In New Zealand you need a building consent for building work unless the law specifically exempts it. The main exemptions are listed in Schedule 1 of the Building Act 2004 (low-risk work such as small sheds, low decks, pergolas, small carports and low retaining walls), plus a separate exemption for small stand-alone dwellings ("granny flats") in Schedule 1A. Even when work is exempt, it must still comply with the Building Code and with your council's district plan rules.

Yes. The Building Act defines building work broadly: work for, or in connection with, the construction, alteration, demolition or removal of a building, including sitework. It is not just houses; Schedule 1 itself deals with fences, retaining walls, decks, tanks and signs. Section 40 of the Building Act 2004 (opens in a new tab) says a person must not carry out building work except in accordance with a building consent. Section 41 then lists the exceptions, the main ones being:

  • work described in Schedule 1 (or Schedule 1A for small stand-alone dwellings)

  • urgent work needed to save or protect life or health, or to prevent serious damage to property, where a consent cannot practicably be obtained first (the owner must then apply for a certificate of acceptance)

  • certain energy work, and a few other specialised categories.

Building without a required consent is an offence. MBIE notes the council can also issue a notice to fix and infringement fines.

Which work is exempt under Schedule 1?#

Schedule 1 has three parts:

  • Part 1 – work that anyone can do, as long as every condition of the exemption is met. Some Part 1 exemptions apply only if a Licensed Building Practitioner (LBP) carries out or supervises the design and construction.

  • Part 2 – sanitary plumbing and drainlaying done by a person authorised under the Plumbers, Gasfitters, and Drainlayers Act 2006.

  • Part 3 – work that is exempt only if a Chartered Professional Engineer (CPEng) designs or reviews it and it is built to that design.

Some commonly used exemptions (Building Act, version as at 8 October 2026):

WorkExempt when (summary)Schedule 1 clause
Repairs and maintenanceComparable products used, in the same position; excludes complete or substantial replacement of structural or fire-safety elements, and repairs to products that have failed the durability requirements (such as leaking cladding)1
Small detached building (shed, sleepout)Up to 10 m², single storey (floor up to 1 m above ground, up to 3.5 m high above the floor), no sanitary facilities or potable water storage; sleeping only if used with a dwelling and no cooking3
Detached building 10–30 m²Same single-storey limits, plus lightweight walls and roof built to B1/AS1, or LBP design and construction, or a CPEng-designed kitset; at least 1 m from any residential building or legal boundary3A, 3B, 43
PergolaAny pergola6
CarportOn ground level, up to 20 m²; 20–40 m² if LBP-supervised or CPEng-designed18, 18A, 44
Deck, platform, boardwalkNot possible to fall more than 1.5 m, even if it collapses24
Retaining wallRetains no more than 1.5 m depth of ground and carries no surcharge (such as vehicles); up to 3 m in a rural zone if CPEng-designed and set back at least its own height20, 41
FenceUp to 2.5 m high (not pool fences)21

Each exemption has its own conditions, and you must meet all of them. MBIE's exempt building work guidance (opens in a new tab) explains every clause with examples. See also Do you need building consent to build a deck? and retaining walls and building consent.

Granny flats. Since 15 January 2026, Schedule 1A allows a new, stand-alone, single-storey dwelling of up to 70 m² to be built without a building consent if strict conditions are met. These include licensed professionals doing the restricted work, a project information memorandum (PIM) before starting, and records sent to the council at completion. See MBIE's granny flats exemption guidance (opens in a new tab).

Can the council exempt work that doesn't fit an exemption?#

Yes. Schedule 1, Part 1, clause 2 lets a city, district or regional council decide that consent is not needed if it considers the finished work is likely to comply with the Building Code, or, if it does not comply, is unlikely to endanger people or buildings. This is the only exemption where the council makes the decision; for every other exemption, the owner decides. Councils may charge a fee, and MBIE advises getting the decision in writing. Discretionary exemptions (opens in a new tab) cannot be used for granny flats.

If my work is exempt, do the rules still apply?#

Yes. Section 17 says all building work must comply with the Building Code, whether or not it needs a consent. Section 42A adds conditions to every Schedule 1 exemption: the work must comply with the Code, an existing building must continue to comply at least as well as it did before, and the work must not breach any other law.

That other law includes the Resource Management Act and your district plan, which may control boundary setbacks, height, site coverage and more. A shed can be exempt from building consent but still need resource consent. See Building consent vs resource consent.

Worked example. You plan a 9 m² sleepout on your side boundary, with no plumbing or cooking, used with your house. MBIE's guidance gives a similar example as exempt under clause 3. But if your district plan requires buildings to be set back from the boundary, you would still need to meet that rule or get resource consent.

Who has to do the work?#

Restricted building work is residential design or construction that needs a building consent (or is a granny flat) and affects a home's primary structure, weathertightness or certain fire safety design. Section 84 requires it to be carried out or supervised by an appropriately licensed LBP, unless the owner holds an owner-builder exemption. MBIE notes that exempt Schedule 1 work is not restricted building work, though an LBP you engage is still accountable for their work. See LBP and non-LBP work.

Exemptions are not retrospective. If work that needed consent was done without one, the owner can apply to the council for a certificate of acceptance (section 96). The council may issue one only if it is satisfied, to the best of its knowledge and belief and on reasonable grounds, that the work complies with the Building Code as far as it could ascertain. MBIE notes this is available for work done from 1 July 1992 onwards, and the rules in force when the work was done apply. A certificate of acceptance does not remove the legal obligation to get consent in the first place.

What should I do next?#

  1. Describe the work exactly: size, height, floor level, distance to boundaries and other buildings, and any plumbing.

  2. Read the matching exemption in MBIE's guidance, or use the government's Can I build it? (opens in a new tab) tool, and check every condition.

  3. Check your district plan, or ask the council, for resource consent rules.

  4. If you are unsure, get advice from your council, an LBP, a registered architect or a CPEng. You can still choose to apply for consent even if work is exempt.

  5. Keep drawings and photos of exempt work, and consider giving copies to the council for the property file.

Key points#

  • Building work needs a building consent unless the law exempts it (Building Act s 40 and s 41).

  • Schedule 1 lists low-risk exempt work; Schedule 1A covers granny flats up to 70 m².

  • Every condition of an exemption must be met; councils can grant discretionary exemptions under Schedule 1 clause 2.

  • Exempt work must still comply with the Building Code (s 17) and the district plan.

  • Unconsented work that needed consent can only be regularised through a certificate of acceptance.

Sources

  1. Building Act 2004 (version as at 8 October 2026) - sections 7, 17, 40, 41, 42A, 42B, 84, 96 and Schedules 1 and 1A (opens in a new tab) - New Zealand Legislation (accessed 20 November 2026)
  2. Building (Exempt Roof-mounted Solar Panel Arrays and Building Work) Order 2025 (opens in a new tab) - New Zealand Legislation (accessed 20 November 2026)
  3. Check if you need consents (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  4. Work you can do without a building consent (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  5. Amendments to building consent exemptions in Schedule 1 of the Building Act 2004 (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  6. Territorial and regional authority discretionary exemptions (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  7. 2.1 Single-storey detached buildings not exceeding 10 square metres (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  8. Restricted building work (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  9. Granny flats exemption guidance (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)

General information about New Zealand rules, not advice for a particular project. Your council confirms whether your project needs building consent, and a suitably qualified professional should check any design.