Building consent vs resource consent: what's the difference?

Building consent checks that building work meets the Building Code. Resource consent covers land use under council plans. Many projects need both.

Author
ArchiSuite
Checked against sources:
Published:
On this page

A building consent and a resource consent answer different questions. A building consent, under the Building Act 2004, confirms that the proposed building work will meet the Building Code, which covers things like structure, weathertightness, fire safety and access. A resource consent, currently still issued under the Resource Management Act 1991 (RMA), is permission to use land or resources in a way your council's district or regional plan does not allow as of right. Examples include building closer to a boundary than the plan permits, subdividing, or discharging stormwater. Many projects need both, and having one does not replace the other.

A building consent authority (usually your local council) must grant a building consent if it is satisfied on reasonable grounds that the Building Code would be met if the work were properly completed to the plans and specifications (Building Act s 49). The council then inspects the work during construction and, at the end, can issue a code compliance certificate.

Building consent is about the building itself: foundations, framing and bracing, cladding and flashings, plumbing and drainage, fire safety, barriers and so on. It does not decide whether the building is allowed on that site, how tall it can be relative to the boundary, or how it looks. Those are planning questions.

Some low-risk work does not need a building consent at all (Schedule 1 of the Building Act). See When do you need building consent?

Under the RMA, councils write plans that set rules for activities that affect the environment:

  • District or city councils prepare district plans covering land use and subdivision, such as the height, appearance and location of buildings and signs, and noise or glare.

  • Regional councils prepare regional plans covering air, water, land and soil, such as water takes and discharges of contaminants.

If an activity is a permitted activity in the plan and meets its conditions, no resource consent is needed (RMA s 87A). Otherwise you need one of the types of resource consent in RMA s 87: a land use consent, a subdivision consent, a coastal permit, a water permit or a discharge permit. For houses, the most relevant one is usually a land use consent for breaching a district plan rule. Examples include a boundary setback, height or site coverage rule.

Two useful tools:

  • Certificate of compliance – if you think no resource consent is needed but want written confirmation, the council can issue a certificate of compliance for a permitted activity (MBIE (opens in a new tab)).

  • Deemed permitted boundary activity – if the only breach is a boundary rule, the activity can become permitted when every affected neighbour gives written approval and signs your site plan (RMA s 87BA).

Building consentResource consent
LawBuilding Act 2004Resource Management Act 1991 (being replaced in stages; see below)
Question it answersWill the building work meet the Building Code?Is this use of land or resources allowed under the district or regional plan?
Who decidesBuilding consent authority, usually the city or district councilCity or district council (land use, subdivision); regional council (water, discharges, coastal)
What is assessedStructure, durability, weathertightness, fire, access, plumbing, energy efficiency and other Code clausesEffects on neighbours and the environment, and plan rules such as building height, location and boundary setbacks
Typical triggersNew buildings, additions, structural alterations, plumbing with new fixtures, decks over 1.5 m fall, retaining walls over 1.5 mBreaching a district plan rule, subdividing, taking water, discharging contaminants, using coastal space
ExemptionsSchedule 1 and Schedule 1A, or a council discretionary exemptionPermitted activities in the plan; boundary approvals under s 87BA
What you end up withBuilding consent, inspections, then a code compliance certificateResource consent, often with conditions that can affect the design

When do you need both?#

You need both when the work is not exempt under the Building Act and it breaches a district or regional plan rule. Common examples:

  • A new garage built closer to the boundary than the district plan allows. It needs a building consent for the structure and a land use consent for the setback breach.

  • A second-storey addition that would exceed the district plan's height limit. It needs a building consent for the structural work and a land use consent for the height breach.

It also works the other way. A 9 m² garden shed can be exempt from building consent under Schedule 1, yet still breach a district plan setback or coverage rule and need resource consent. Exempt building work must still not breach any other law (Building Act s 42A).

Which should you apply for first?#

There is no rule that you must apply in a particular order, but the two are linked. If the council considers that a required resource consent has not been obtained and it will or may materially affect the building work, it must issue a certificate under Building Act s 37. That certificate says that no building work may proceed (or only to a stated extent) until the resource consent is obtained.

In practice, many people:

  1. check the district plan, or ask the council's planning team, early in the design

  2. apply for resource consent first, or at the same time as building consent, so planning conditions can be built into the consent drawings

  3. lodge the building consent once the design is settled, then start work only when both are in place.

Is the RMA being replaced?#

Yes, in stages. The Planning Act 2026 (for land use and development) and the Natural Environment Act 2026 (for natural resources) received Royal assent on 30 September 2026. Most of the Planning Act came into force on 1 October 2026. However, its consenting provisions (new "planning consents") and the repeal of the RMA start on dates to be set by Order in Council. Any part not yet in force by 30 September 2030 starts then.

As at 20 November 2026:

  • you still apply to your local council for resource consent, and councils process applications under the RMA and existing RMA plans (planning.govt.nz (opens in a new tab))

  • existing RMA resource consents continue and will later become planning consents, natural resource permits, or both

  • since 30 October 2026, councils assessing district land use consents must disregard certain residential matters, such as glazing area, balconies, outdoor living space, internal layout and unit size (RMA s 104(1A)).

These reforms replace the RMA. They do not replace the Building Act: building consents continue under the Building Act 2004.

Key points#

  • Building consent = Building Act, Building Code compliance of the work itself.

  • Resource consent = RMA (for now), whether the activity is allowed under district or regional plans.

  • You may need one, both or neither; an exemption from one is not an exemption from the other.

  • A missing resource consent can stop building work through a Building Act s 37 certificate, so sort out planning early.

  • The RMA is being replaced by the Planning Act 2026 and Natural Environment Act 2026, but resource consents are still applied for under the RMA during the transition.

Sources

  1. Building Act 2004 (version as at 8 October 2026) - sections 17, 37, 40, 49 (opens in a new tab) - New Zealand Legislation (accessed 20 November 2026)
  2. Resource Management Act 1991 (version as at 30 October 2026) - sections 9, 87, 87A, 87BA, 104 (opens in a new tab) - New Zealand Legislation (accessed 20 November 2026)
  3. Planning Act 2026 (2026 No 70, as enacted 30 September 2026) - section 2 Commencement (opens in a new tab) - New Zealand Legislation (accessed 20 November 2026)
  4. Natural Environment Act 2026 (2026 No 71) (opens in a new tab) - New Zealand Legislation (accessed 20 November 2026)
  5. Do you need resource consent? (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  6. Check if you need consents (opens in a new tab) - MBIE (building.govt.nz) (accessed 20 November 2026)
  7. Consents and notices of requirement during the transition (opens in a new tab) - New Zealand Government (planning.govt.nz) (accessed 20 November 2026)
  8. Homeowners and landowners (opens in a new tab) - New Zealand Government (planning.govt.nz) (accessed 20 November 2026)
  9. Planning Act 2026 (opens in a new tab) - Ministry for the Environment (environment.govt.nz) (accessed 20 November 2026)
  10. Resource Management Act 1991 (opens in a new tab) - Ministry for the Environment (environment.govt.nz) (accessed 20 November 2026)

General information about New Zealand rules, not advice for a particular project. Your council confirms whether your project needs building consent, and a suitably qualified professional should check any design.