Calculator guide · CALC-049

Timber Pole Retaining Wall

Design a timber pole retaining wall for up to five retained heights. The earthquake load is set from the project address, and you can enter a design groundwater depth. Get the pole size, pole density, sock diameter and embedment depth for each height.

On this page

The Timber Pole Retaining Wall calculator designs a cantilevered timber pole wall with timber rails, for up to five retained heights in one calculation. For each height it gives the pole size and density, the diameter of the concrete-filled hole (the sock) and the embedment depth. It sets the earthquake load from the project address, and it can allow for a design groundwater level in front of the wall.

Timber Pole Retaining Wall · CALC-049

One calculation covers up to five different wall heights.

Use it when

  • Retained heights up to 3.0 m.
  • Ground behind up to 20°; ground in front level or falling at up to 5°.
  • Uniform permanent surcharge up to 12 kPa.
  • Pole spacing from 1.2 to 1.5 m.
  • Earthquake wall cases 3, 4 and 5 (Importance Level 2), with the site acceleration taken from the project address.
  • One design groundwater depth below the ground in front of the wall, or no groundwater.

Results

  • Pole sizes, pole density and embedment depths.
  • Concrete sock (hole) diameters.
  • Timber rail options and wall schedules.

Limits

  • Not for walls that form part of a building or directly support one.
  • Not for walls interacting with other nearby retaining walls. (Contact ArchiSuite if you’re unsure about wall interaction.)
  • Not for groundwater above the ground in front of the wall.

Before you start#

This calculator reads these values from the active project's Project Settings:

  • Project Address. Choose the site address from the address search, so that ArchiSuite can place the site. Each time you analyse, ArchiSuite looks the address up again and sets the design earthquake acceleration, Amax, from it. If the address cannot be placed, nothing is analysed.

  • Territorial Authority. It decides whether the site is in the Canterbury earthquake region (Christchurch City, Selwyn District or Waimakariri District).

  • The Geotechnical Properties section. Fill in all four report details (Geotechnical Engineering Company Name, Report Reference / Revision, Report Title, Report Date) and all four soil properties (Backfill soil friction angle, φb, Backfill soil unit weight, γb, Founding soil friction angle, φf, Founding soil unit weight, γf). A retaining wall cannot be analysed until every one of these is filled in. Save with Update Project.

This calculator does not use Earthquake Zone or Soil Class. Project Settings still asks for them when Retaining walls is ticked under What are you designing?, so fill them in as usual. They do not change this design.

Project Settings accepts soil friction angles from 20° to 36°. This calculator is stricter for the backfill: it needs Backfill soil friction angle, φb between 26° and 36°.

How the earthquake acceleration is set#

The design is for an Importance Level 2 wall and the 500-year earthquake. Amax is the peak ground acceleration for that earthquake, in g.

  • ArchiSuite uses Table A1 of Earthquake Geotechnical Engineering Practice, Module 1 (MBIE / NZGS, November 2021). The table lists 500-year values for towns.

  • It finds the two listed towns nearest the site and uses the higher of their two values.

  • In Auckland and Northland, the table's lower bound of 0.19 g applies.

  • A site in the Canterbury earthquake region takes at least 0.40 g. This is a minimum adopted for the region. It does not depend on the site's subsoil class. Where the two nearest listed towns carry more, for example near Arthur's Pass or Darfield, the higher value is used.

  • The calculator is not used for sites on the Chatham Islands. Analysing one brings up the Important Design Limitation dialog. See Common errors, below.

The towns, their distances and the value adopted are shown with the results and printed in the calculations.

Have these ready from the site and the geotechnical report:

  • Each retained height you want designed, in mm (up to five).

  • The slope of the ground behind the wall, and any permanent surcharge on it.

  • The backfill and founding soil friction angles and unit weights. These are normally the same values you entered in Project Settings.

  • Whether there is a design groundwater level and, if so, its depth below the ground in front of the wall (see Groundwater, under The inputs).

  • The pole spacing you want, and the wall case that describes the wall's situation.

Step by step#

  1. In the sidebar, click All Calculators. Choose the Retaining Walls tab, then the Timber Pole Retaining Wall card. (The Timber Pole Retaining Wall (Embedded Cantilever, Beta) card is a different calculator.)

  2. On the Timber Pole Retaining Wall page, click New Timber Pole Retaining Wall. If the project has none yet, click Add Timber Pole Retaining Wall.

  3. In General Info, enter a Calculation Name (for example TPRW1).

  4. In Retained Heights (A), enter Height 1 in mm. Click Add Height to add more, up to five. Use the bin icon to remove a height.

  5. In Geotechnical & Soil Parameters, enter Ground slope above wall, Permanent surcharge, Backfill soil unit weight, γb, Backfill soil friction angle, φb, Founding soil friction angle, φf and Founding soil unit weight, γf.

  6. Still in Geotechnical & Soil Parameters, answer Groundwater present? with Yes or No. There is no default. If you choose Yes, enter Design groundwater depth below ground level in front of the wall (mm).

  7. In Structural & Layout Parameters, enter Pole spacing and choose the Wall case (Case 3, Case 4 or Case 5). No case is selected at first: choose the one that describes the wall's situation.

  8. Click Analyse Data. ArchiSuite first reads the latest saved Project Settings:

    • If the geotechnical information is incomplete, Geotechnical information required opens and nothing is analysed. Click Close, complete Project Settings, then come back and click Analyse Data again. Your form values are kept.

    • If your soil inputs differ from the project's soil properties, Check geotechnical values opens. Click Review inputs to go back and change them. Or click Continue to analyse with the values exactly as you entered them.

    • ArchiSuite then looks up the project address to set Amax. If it cannot, an error message says why and nothing is saved. See Common errors, below.

  9. The Summary table appears below the form, with one row per height. Below it are the Earthquake design basis and, where they apply, the Design notes.

  10. If any height fails, Important Design Limitation opens. Click Back to return to your inputs, which keep their values, and change them. Or click Request Specific Design to ask ArchiSuite for a specific engineering design.

  11. When every row shows Pass, click Accept. You will see "Calculation accepted successfully!", the button changes to Accepted, and the calculation is added to Project Outputs.

To change a saved calculation, open it from the Timber Pole Retaining Wall list. Edit the inputs and click Update Analysis. Every analysis looks up the project address again.

The inputs#

Retained Heights (A). Each height is the retained height of soil the wall holds back, in mm, from the ground in front of the wall to the ground behind it. Do not include the embedded length of the poles. Each height is designed on its own, with the same soil, surcharge, spacing, wall case and groundwater. For example, use extra heights along a stepped wall.

Geotechnical & Soil Parameters. Ground slope above wall is the slope of the ground behind the wall, from 0° (level) to 20°. Permanent surcharge is a load that is always on the ground behind the wall, from 0 to 12 kPa. The backfill values describe the soil behind the wall: Backfill friction angle (26° to 36°) and soil unit weight (14 to 20 kN/m³). The founding values describe the natural ground the poles are embedded in: Founding friction angle (20° to 36°) and the founding soil unit weight (14 to 20 kN/m³). The backfill values drive the soil pressure on the wall. The founding values drive the ground's resistance around the embedded poles.

Structural & Layout Parameters. Pole spacing is the centre-to-centre distance between poles, from 1.2 m to 1.5 m. One spacing applies to every height in the calculation.

Groundwater#

Groundwater present? Choose Yes where the geotechnical information gives a design groundwater level. Choose No only where it shows there is no groundwater to design for.

Design groundwater depth below ground level in front of the wall (mm) is the design groundwater depth. Measure it like this:

  • Down from the ground surface immediately in front of the wall, at the base of the exposed wall face. Positive is downward: 2000 means groundwater 2.0 m below that ground. 0 means groundwater at that ground level.

  • It is a depth, not a site level (RL). Do not measure it from the ground behind the wall, the top of the wall or the bottom of the poles.

  • One value applies to every height. Where the ground or the groundwater level varies along the wall, work out the depth at each section and enter the shallowest.

  • Groundwater above the ground level in front of the wall is outside this calculator's scope. A negative depth is refused.

For each height, the calculator first designs the wall without groundwater. Then:

  • If the design groundwater level is at or below the bottom of the poles, that design stands. Groundwater there does not change it.

  • If the level is within the embedded length of the poles, the wall is designed again as though the groundwater were at the ground level in front of the wall. This is on the safe side, and it can add a lot of embedment. The minimum embedment also rises (see Limitations).

  • The earthquake case is always analysed without groundwater.

Because each height is checked against its own poles, a short wall can stay dry while a taller wall on the same entry is designed with groundwater.

The diagram above the form draws the groundwater level as you entered it. It is a picture of your input only. The results say how the groundwater was treated.

Wall case and the earthquake load#

The Wall case describes the wall's situation, using the cases of Figure 4.1 in Earthquake Geotechnical Engineering Practice, Module 6 (MBIE / NZGS). It sets the wall displacement factor, Wd, which reflects how much permanent movement the wall may undergo in the design earthquake.

Wall caseSituationWd
Case 3Downslope wall supporting building foundations0.5
Case 4Upslope wall within 1.5 times the retained height of a building0.4
Case 5Wall providing access or services, such as a driveway0.3

Include buildings, access and services on neighbouring properties. If more than one case could apply, use the one with the higher Wd. Walls that form part of a building or directly support one (Cases 1 and 2), and the Importance Level 1 case (Case 6), are not covered.

The seismic coefficient for each height is kh = Amax × 1.2 × Wd, where 1.2 is the topographic amplification factor. If kh is more than 0.30, the height fails as outside the design method. The value is never reduced to fit. For example, Amax 0.68 g with Case 3 gives kh = 0.408, so no design is produced. In high-hazard places this can rule out Case 3, and sometimes Case 4, at every height.

Click the (i) beside Wall case to open the ArchiGuide drawer. It shows the cases of Figure 4.1 from Module 6, and notes that Cases 1, 2 and 6 are outside this calculator's scope. Click a figure to enlarge it.

The (i) beside Wall case shows the Module 6 wall case figures
  • Height 1Required

    more than 0 and up to 3000 mm

    If not: “Must be ≤ 3000 mm”

  • Height 2Optional

    more than 0 and up to 3000 mm

    If not: “Must be ≤ 3000 mm”

  • Height 3Optional

    more than 0 and up to 3000 mm

    If not: “Must be ≤ 3000 mm”

  • Height 4Optional

    more than 0 and up to 3000 mm

    If not: “Must be ≤ 3000 mm”

  • Height 5Optional

    more than 0 and up to 3000 mm

    If not: “Must be ≤ 3000 mm”

  • Ground slope above wallRequired

    0 to 20 °

    If not: “Maximum is 20°”

  • Permanent surchargeRequired

    0 to 12 kPa

    If not: “Maximum is 12 kPa”

  • Backfill soil unit weight, γbRequired

    14 to 20 kN/m³

    If not: “Maximum is 20 kN/m³”

  • Founding soil unit weight, γfRequired

    14 to 20 kN/m³

    If not: “Maximum is 20 kN/m³”

  • Backfill soil friction angle, φbRequired

    °

  • Founding soil friction angle, φfRequired

    20 to 36 °

    If not: “Maximum is 36°”

  • Pole spacingRequired

    m

  • Wall caseRequired

    As shown on the form

  • Groundwater present?Required

    As shown on the form

  • Design groundwater depth below ground level in front of the wall (mm)Optional

    mm

Read from Timber Pole Retaining Wall (CALC-049, version 1.1.0) as it runs today. The form may also show its own limit beside an input.

Worked example#

This example was worked out with ArchiSuite's own calculation code. It is not a design for your site.

Site: Amax 0.30 g (for example Tauranga, where the two nearest listed towns, Tauranga and Mount Maunganui, both carry 0.30 g). The geotechnical report details are complete, with all four soil properties set to φ 30° and γ 18 kN/m³.

Inputs: Height 1 1000, Height 2 2000, Height 3 3000 mm; Ground slope above wall 0°; Permanent surcharge 5 kPa; backfill and founding unit weights 18 kN/m³; backfill and founding friction angles 30°; Groundwater present? No; Pole spacing 1.2 m; Wall case Case 3. So kh = 0.30 × 1.2 × 0.5 = 0.18.

The Summary shows:

CaseHrPole SEDDensitySock DcSpacing SEmbedment LStatus
H11,000 mm200 mmNormal density350 mm1.20 m1.8 mPass
H22,000 mm325 mmHigh density500 mm1.20 m3.4 mPass
H33,000 mm450 mmHigh density600 mm1.20 m5.0 mPass

The same wall with Groundwater present? Yes and a depth of 2500 mm:

  • H1 is unchanged. Its poles stop 1.8 m down, above the groundwater, so the design notes say the poles are designed without groundwater.

  • H2 becomes a 375 mm high density pole in a 600 mm sock, embedded 4.8 m. The groundwater is within its embedment.

  • H3 fails: "No compliant design: the largest pole tried (450 mm high density, 600 mm sock) does not have enough pole strength." The calculation cannot be accepted until H3 is changed or removed.

Results#

The Summary table has one row per height:

  • Case: H1 to H5, in the order you entered the heights.

  • Hr: the retained height.

  • Pole SED: the pole size (small end diameter).

  • Density: Normal density or High density. Normal density is tried first. If it would need a small end diameter of 300 mm or more, the height is redesigned with a high density pole.

  • Sock Dc: the diameter of the concrete-filled hole around the pole.

  • Spacing S: the pole spacing you entered.

  • Embedment L: the embedment depth of the pole below the ground in front of the wall, rounded up to the next 0.1 m.

  • Status: Pass or Fail. A height that fails shows "-" instead of sizes.

Earthquake design basis gives the importance level and return period, the Amax used and where it came from: the listed town it was taken from, or the minimum adopted for the Canterbury earthquake region. It lists the two nearest listed towns with their values and distances, and the source edition of Module 1 Table A1.

Design notes appear under the table:

  • For a height that fails, the reason, in the calculator's own words. See Common errors, below.

  • For a height that passes when Groundwater present? is Yes, how the groundwater was treated. One of:

    • "The design groundwater level is below the underside of the poles, so it does not act on the soil the poles bear against. The poles are designed without groundwater."

    • "The design groundwater level is at the ground level in front of the wall. The static case takes the founding soil as submerged from that level. The earthquake case is analysed without groundwater."

    • "The design groundwater level is within the pole embedment. The static case takes the founding soil as submerged from the ground level in front of the wall, which is more severe than groundwater at the entered depth. The earthquake case is analysed without groundwater."

The documents also give the governing check for each height and the timber rail options, with the maximum retained height each rail arrangement can hold.

After you accept, the calculations, project summary and drawings are prepared from Project Outputs. See Pay for and download your documents.

Limitations#

  • Up to five retained heights, each more than 0 mm and no more than 3000 mm. All heights share the same soil, slope, surcharge, spacing, wall case and groundwater. For different values, use separate calculations.

  • Ground slope above wall from 0° to 20°, and Permanent surcharge from 0 to 12 kPa.

  • Unit weights from 14 to 20 kN/m³. Backfill soil friction angle, φb from 26° to 36°, and Founding soil friction angle, φf from 20° to 36°.

  • Pole spacing from 1.2 m to 1.5 m. One spacing is used for all heights.

  • Importance Level 2 and the 500-year earthquake only. Wall cases 3, 4 and 5 only. A height with kh above 0.30 fails.

  • Amax comes from the towns listed in Module 1 Table A1, not from a site-specific study. In remote areas the nearest listed towns can be a long way from the site.

  • Sites on the Chatham Islands are not covered. Request a specific design.

  • One design groundwater depth for all heights, at or below the ground in front of the wall. Groundwater within the embedment is designed as though it were at that ground level. The earthquake case is analysed without groundwater.

  • The pole design allows for ground in front of the wall that falls away at 5°, by lowering the ground level used for the pole design (Wood, 2022). Steeper ground in front of the wall is not covered.

  • The embedment is at least 1.5 times the design height, or 2.0 times where groundwater is designed at the ground level in front of the wall. The design height includes the allowance for the falling ground in front. Where that minimum alone would be deeper than the 6.0 m search limit, the height fails.

  • The only load input is a uniform permanent surcharge. There are no inputs for line loads, point loads or vehicle loads.

  • The rail table does not check rail shear, rail deflection, the earthquake case or the rail to pole fixings.

  • Every height must pass before the calculation can be accepted.

  • Each analysis needs the address service to place the site. If the service cannot be reached, try again shortly.

Common errors and how to fix them#

  • Geotechnical information required: "Complete the geotechnical report details and soil properties in Project Settings before analysing this retaining wall." Fill in every field in the Geotechnical Properties section of Project Settings, save, and analyse again. Example text and fillers such as "TBC" do not count. See Project Settings missing.

  • Check geotechnical values: "These inputs differ from the project geotechnical properties. Check they are suitable before continuing." Click Review inputs and correct the values. Or, if the different values are intended, click Continue.

  • "Project Settings could not be loaded, so the geotechnical information could not be checked. Try again." Check your connection and click Analyse Data again.

  • "The project has no site address, so the earthquake acceleration (Amax) for this calculator cannot be assigned. Enter the site address in Project Settings." Enter the Project Address in Project Settings, save, and analyse again.

  • "The project address could not be found by the address service, so the earthquake acceleration (Amax) for this calculator cannot be assigned. Select the site address from the address search in Project Settings." Retype the Project Address and pick it from the list.

  • "The project address matches more than one location, so the earthquake acceleration (Amax) for this calculator cannot be assigned. Select the full site address from the address search in Project Settings." Pick the full address, with street number, suburb and town, from the list.

  • "The address service could not be reached, so the earthquake acceleration (Amax) for this calculator cannot be assigned just now. Try the analysis again shortly." Nothing is wrong with your inputs. Wait a little and click Analyse Data again.

  • "The address service is not configured, so the earthquake acceleration (Amax) for this calculator cannot be assigned." This is a fault on ArchiSuite's side. Contact ArchiSuite.

  • "Groundwater above the ground level in front of the wall is outside the scope of this calculator. Enter the depth below that ground level as zero or a positive number." Enter the depth below the ground in front of the wall, as 0 or more. If the groundwater really is above that ground, see When no calculator fits.

  • "Required" under Groundwater present?, Design groundwater depth below ground level in front of the wall (mm) or Wall case. These have no default. Answer them before you analyse.

  • "Must be ≤ 3000 mm" or "Must be > 0 mm" under a height. Each retained height must be more than 0 and no more than 3000 mm.

  • "Minimum is 26°" under Backfill soil friction angle, φb. The backfill angle must be at least 26°, even though Project Settings accepts lower values.

  • "Minimum is 1.2 m" or "Maximum is 1.5 m" under Pole spacing. Enter a spacing from 1.2 to 1.5 m.

  • A height shows Fail and the design note starts "Outside the design method: kh = Amax x Atopo x Wd = ...". The earthquake load at this location is above the method limit for the wall case. Check the wall case is right. A case with a lower Wd is only correct if it describes the wall's situation. Otherwise, request a specific design.

  • A height shows Fail and the design note starts "No compliant design: the largest pole tried ...". No pole in the schedule is strong enough or embedded enough. Try a closer pole spacing, or check the soil values and groundwater depth. The note ends "Groundwater within the pole embedment is included in this design." when the groundwater made the difference.

  • A height shows Fail and the design note starts "No design within the search limit: the minimum embedment set for this calculator ...". The minimum embedment alone would be deeper than 6.0 m. This is not a shortfall of pole strength. Reduce the height, or request a specific design.

  • A height shows Fail and the design note starts "Outside the design method:" with another reason, for example ground behind the wall that is too steep for the earthquake case. Check the slope and soil values.

  • Important Design Limitation: "The Timber Pole Retaining Wall calculator is not suitable for sites on the Chatham Islands." The project address is on the Chatham Islands. Click Request Specific Design, or Back to leave the calculation unchanged. See When no calculator fits.

  • Important Design Limitation: "Your design parameters fall outside ArchiSuite's design limitations." At least one height failed. Click Back and change the inputs, remove the failed height, or click Request Specific Design. See When no calculator fits.

  • A message starting "This calculation cannot be accepted or issued." when you click Accept. If it goes on "The project address or council has changed since this calculation was analysed. Analyse it again so that the earthquake acceleration (Amax) is the one for the site.", click Update Analysis, check the results, and accept again. Otherwise, at least one height has failed: get every height to pass first.

  • "Permission denied" when you update or delete. Only team admins and editors can change saved calculations. See Teams and permissions.

  • "This calculation has been issued, so it cannot be changed. Use Revise Calculation on Project Outputs to make a revised version." See Revise an accepted calculation.

Was this helpful?

How-toProject SettingsEvery field on the Project Settings page - what it means, the accepted options and limits, which calculators use it, and what happens to existing calculations when you change it.Read TroubleshootingProject Settings Missing or Out of RangeFix messages such as "Roof Pitch is missing or out of range…" or "Project Settings … is required before running this calculation" by completing Project Settings.Read TroubleshootingWhy an Input Is RefusedWhat the red messages under an input and the error toasts after Analyse mean, grouped by cause, with the fix for each.Read How-toCheck and Accept ResultsHow to read a calculator's results, choose a passing member, and press Accept so the calculation moves into Project Outputs.Read How-toPay and Download Your DocumentsPay for accepted calculations on Project Outputs, or send the property owner a payment link, then download the Project Summary, Calculations and Drawings.Read How-toRevise an Accepted CalculationA paid calculation is locked. Change it through a draft revision, then Update & Accept and pay. Your issued documents stay in place until the revision replaces them.Read Calculator guideTimber Pole Retaining Wall (superseded)Design a timber pole retaining wall for up to five retained heights. Get pole sizes, hole diameters, embedment depths and timber rail options for each height.Read Calculator guideCantilever Masonry Retaining WallDesign a reinforced concrete block cantilever retaining wall on a strip footing for up to five retained heights, with the toe, heel and shear key sized for you.Read Calculator guideMasonry Foundation WallDesign a reinforced concrete block foundation or basement wall propped at the top, for one retained height up to 2.5 m, including roof and wall loads on the footing.Read How-toChoose the right calculatorHow calculators are grouped in the app and on the public site, and a quick table to pick the right one from what the member or wall supports.Read How-toWhen no calculator fitsWhat to do when your design is outside every calculator - submit a design request to ArchiSuite, contact the team, or suggest a calculator through Feedback & Ideas.Read How-toTeams and permissionsHow ArchiSuite teams work, how to switch your active team, invite people, accept or decline an invitation, and what Admins, Editors and Viewers can do.Read